Metta Data Center

Owner : PT. MettaDC Teknologi

Location : Jababeka

Total IT Load : 8 MW

Year : 2022-2023

Scope Of Work:

  • Power System from LV Switchgear to power distribution in data hall
  • Containment system for Data Hall
  • UPS System for Datahall & Mechanical System
  • Chiller System and Fan Wall Unit as well as CRAH system

 

Construction date: 2022-2023
Location: Jababeka