Equinix JK1 Data Center
Equinix JK1 Data Center
Owner : Equinix jk2
Location : Jakarta
Total IT Load : 2.6 to 70 MW
Year : 2025-Current
Scope Of Work:
- UPS & STS System Installation PDU & RPP Installation MV Switchgear & Transformers Main LV Switchgear Generators & Bulk Fuel Oil .
- Works General Electrical Installation (All Levels & Rooftop)Panel Positioning (TOU, FFU, GCP, Critical Panels)Auxiliary Power & Control Cabling (RMU Lv.2 – Lv.7)Cable Ladder & Conduit Installation MV & LV Cable Laying Gland, Grounding & Termination
- UPS Installation Lithium Battery System ConnectionFan Wall & CRAH System Chiller Pump Power & Support (Rooftop)
Verification Grounding & Lightning Protection Final Inspection & Handover